Extraction

Shift Passdown Board

Carry Over (0)

No carry-over items — clean handoff!

This Shift (2)

Medium
OPEN

Overtime approval needed for weekend

Extraction department needs 4 operators for Saturday day shift (0600-1800) to complete batch E-2024-156 which is behind schedule due to solvent delivery delay. Overtime request form submitted to plant manager. Please confirm approved operators by Thursday EOD so we can post the schedule. Volunteers: J. Rodriguez, M. Garcia, T. Wilson, R. Martinez, P. Lee.

Frank Robinson4:12 PM
0/30 ack
Medium
OPEN

Extraction solvent delivery delayed

Scheduled delivery of hexane solvent from ChemSupply Corp was delayed due to trucking issue. New ETA is tomorrow morning 0800. Current tank level at 35% which is sufficient for approximately 18 hours of operation. Procurement has been notified. If level drops below 20%, reduce extraction rate by 50%.

Stephen Torres4:12 PM
0/30 ack