Utilities & Boiler

Shift Passdown Board

Carry Over (0)

No carry-over items — clean handoff!

This Shift (2)

Critical
OPEN

Waste water pH out of spec

Wastewater discharge pH reading at 10.2 at 15:45 - above permitted limit of 9.0. Increased acid dosing pump rate from 15% to 35%. pH trending downward - currently at 9.5 at 16:30. Root cause appears to be caustic cleaning discharge from blending area CIP system. Notified blending supervisor to stagger CIP cycles. Environmental regulatory reporting may be required if pH exceeded limit for more than 1 hour.

Jeffrey Castillo4:12 PM
0/28 ack
Low
OPEN

Boiler #2 scheduled for inspection

Boiler #2 is scheduled for annual insurance inspection on Thursday. Need to begin cooldown procedure on Wednesday evening shift. Boiler #1 and #3 can handle full plant load. Notify all department supervisors that steam pressure may dip during switchover. Inspector from Hartford Steam will arrive at 0700 Thursday.

Jeffrey Castillo4:12 PM
0/28 ack